Chennai Metro trains will start running in 7 months. This was announced by the Mtero Rail Project Director, Mr. Narasimha Prasad.
The trains will run at an average speed of 40 m per hour. The 2nd day
of test run between Koyambedu and Ash ok Nagar covering a distance
of 5.7 km was completed successfully.
Press reporters and some officials participated in the 2nd day
test-run. The train was run at 40 km per hour. It took 20 minutes. The train
ran without stopping in the stations in between during the first test-run for
the day and reached Ashok Nagar in 8 minutes. While returning, it stopped at
the stations. The test-run will continue. It will be gradually extended up to
St. Thomas Mount.
The first quota of 5 trains has been imported from Brazil. The
nalance 33 trains will be manufactured in Andhra Pradesh.