Kumari Palany & Co

Grid Assimilations – Bridge Power Deficit during Summer

Posted on: 19/Mar/2014 11:41:48 AM
Callous summer has been showing its head in Chennai. People who have faced elevated temperature and frequent power cuts have been anxious about the current circumstances this year.

The officials of TANGEDCO are very affirmative in their words about the stretchy power cuts, by providing the present power generation capacity of the State’s Thermal Plants and the probable wind production anon in May.

As per the worked out plan of the Chennai Corporation for this summer, the extent of the planned power cuts has been brought down to five hours from eight hours, pointed by the TANGEDCO, senior official.

Because of yield of about 1,200 MW and 750 MW power from both the new thermal plants including North Chennai Thermal Power Station (NCTPS) and Vallur Thermal Power Project respectively, has deliberately reduce the state’s scarcity of over 2000 MW.

The integration of the southern grids and northern grids along with the authorization of the Raichur-Sholapur transmission line with a potency of about 765 KV facilitates the alternative choice of drawing from the power-redundant States; hence residents may feel a pleasant summer this year, confidently expressed by an official of the Tamil Nadu Transmission Corporation Limited (TANTRANSCO).

Power purchase agreement of 3,330 MW for subsequent 15 years signed by Chief Minister in the Assembly will ease the power deficit.