Chennaites very soon you will get new power connections in 8 days. No running from pillar to pillar to get your work done. The Tamil Nadu Generation and Distribution Corporation will start a facility of online submission of forms for the new electricity connections very soon. This would be a great boon to the citizens of Chennai.
The Power Ministry, after taking stock of the procedures involved in getting power connections from various distribution companies (discoms) in the country, formulated a policy called ‘3-step-procedure’ to get an electricity connection within 15 days against the present one-month period. The three-step formula on submission of online application involved field inspection to be carried out within three days; the process of estimate preparation, load sanction and intimation of fee deposit to be done within four days and electricity to be connected along with meter installation within eight days.