Deadline for completing the Adambakkam
Bridge is fixed, it’s
expected to be completed by March 2011.Its an important one bridging
Velacherry, Adambakkam, Ullagaram and St Thomas Mount. The cost of construction
of the is Rs 15.5 Crores. The six lane bridge of 350 meters long. MRTS will also run through the bridge to some
extent before it gets diverted to St
Thomas Mount... The construction of this bridge got stalled
in interval as 5 Km stretch between GST
road and Velachery got into acquisition wrangles with parties frequently
approaching the courts for settlements.